7ME7: PROD. & INDL. ENGG. LAB. - II

  1.  

    1. To study CNC - Lathe machine, Tool holders and Practice on the manual control

    2. To prepare the program for the job shown in drawing shown in drawing run the programme and plot it.

    3. To prepare a Programme for job given in drawing

  2.  

    1. To study the capstan lathe, tool holders and attachments.

    2. To prepare the givenjob as drawing

    3. To prepare a process chart and flow diagram for the above job

  3. To prepare part program for the given drawing for Spectra Mill and verify it.

  4. Design a Die & Punch set for Blanking & Punching equation for the given job in drawing and prepare the job

  5. To measure flatness and surface defects in the given test piece with the help of monochromatic check light and optical flat.

  6. To plot the composite errors of the given set of the gears using composite gear tester.

  7. To measure and temperature at the tool point chip thermocouple technique. Industrial Engineering:

  8. Given a set of marble balls of different colours - Verify the binomial distribution of the number of defective balls by treating the balls with a red colour to be defective. Plot a p-chart by taking a sample n=20 and establish control limits.

  9. Find the distribution of the numbered card board chips by random drawing one at time with replacement make 25 subgroups of size 5 and 10 and find the type of distribution of average in each case, comment on your observations.

  10. To prepare man machine chart for drilling two holes in a plate 10 mm thick on a radial drilling m/c.

  11. To draw two hand process chart for bulb holder assembly and to suggest a satisfactory layout.

  12. To find out standard time for the above assembly.

  13. Plot the operating characteristics curve for a single sampling attribute plan for n=20, c=1,2,3,4,5 compare the actual curve with theoritical o.c. curve using approximation for the nature of distribution. Designate the red balls to be defective.